The water dam was delivered to 900 Innes and prepared for installation. The dam was placed along the shoreline during low tide, and rolled out as tides rose. Pumps and hoses were deployed in the Bay to allow for the filling of the water dam with bay water over a 2 day period to help stabilize the dam. The contractor will continue to mobilize equipment (field trailers, excavator platforms, holding tanks, concrete barriers, etc) in the coming weeks. Work is anticipated to be light as the shoreline area drains of water.

Crews install the water barrier at India Basin

Crews install the water barrier at India Basin