We are getting close to completing first phase work at 900 Innes and anticipate removing the water barrier next month. From there, we will have some follow-up work with the aim to finish remediation by the end of June. Stay tuned for an event to celebrate this milestone!
For the second phase, The 900 Innes Park Development Project, we are in the process of negotiating a contract with Swinerton to build the park. We hope to share more details in the next few months and anticipate breaking ground on the second phase of construction in late summer.